Skip links and keyboard navigation

Construction notifications

Construction notifications are issued for works across the project. See below for details of the latest works on the Gateway Upgrade North.


To receive regular project updates, find out more about consultation activities, and keep up to date with construction and traffic impacts once works commence, register your details here.

Latest notifications

16 March – Temporary pathway closure extended: Gateway Motorway between Carl Place and John Fisher Drive

Due to ongoing pathway upgrades, sections of the shared pathway located alongside the northbound lanes of the Gateway Motorway, between Carl Place and John Fisher Drive, Bracken Ridge, will remain closed to all users until mid to late 2018.

Find out more information

14 March – Construction of new Gateway Motorway gantry: Deagon

Works will be undertaken during March and June to install a new overhead gantry on the Gateway Motorway at Deagon – adjacent to Nearra Street.

Find out more information

5 March – Temporary off-ramp closure: Bicentennial Road

The Bicentennial Road northbound off-ramp will be temporarily closed to all traffic continuously from 8pm Friday 16 March until 5am Monday 19 March 2018. This temporary closure is required to facilitate asphalting and line marking works.

Find out more information

28 February – Depot Road construction works: Braun Street to the Gateway Motorway ramps

The final stage of the Depot Road upgrades continue, with the remaining construction activities expected to be finalised in mid-2018. Since the final stage of the road upgrade began in late 2017, a number of key construction milestones have already been achieved. The remaining works at this location will continue to be undertaken during the day and at also at night.

Find out more information

28 February – Gateway Motorway works update: Nudgee and Nundah Creek

During March and April, major works will continue through Nudgee, including works on the Gateway Motorway and the Nundah Creek bridges. The final round of piling activities for the Nundah Creek bridge foundations is now complete, allowing above-ground structural works to commence.

Find out more information

21 February – Works update: Deagon Deviation

As part of finishing work on the Depot Road northbound on-and-off ramps, concrete barrier installation and asphalting works will be undertaken from late March 2018.

Find out more information

21 February – Gateway Motorway road pavement and safety improvements: Bracken Ridge to Bald Hills

As part of the Gateway Upgrade North project, road pavement and motorway safety improvements between the Deagon Deviation and Wyampa Road overpass are progressing well, with works currently scheduled to continue until mid-2018.

Find out more information

21 February – Gateway Motorway overhead gantry installation: Deagon Deviation

From late February, work will be undertaken to construction four new gantries over to top of the motorway at the Deagon Deviation. This work will mostly take place at night when traffic volumes are lower.

Find out more information

2 February – Bracken Ridge-Barfoot Street intersection upgrade and signalisation

Work is continuing to upgrade the Bracken Ridge-Barfoot Street intersection with traffic signals. Upcoming activities include the temporary removal of the concrete panels along the Bracken Ridge Road off-ramp, as well as the installation of services such as underground drainage and electrical conduits.

Find out more information

1 February – Heavy vehicle rest stop: Nudgee

As part of the project, a new heavy vehicle rest stop is being construction on the old motorway alignment near the Nudgee Service Centre. Once complete, the rest stop will help to east on-street heavy vehicle parking along Nudgee Road and provide a place for trucks to stop during their travels.

Find out more information

1 February – Sandgate Road/Braun Street bridges: Works scheduled for February and March 2018

During February and March, works will continue on a number of construction activities around the Sandgate Road/Braun Street bridge work areas in Boondall. Works include drainage, steel fixing and large concreting pours.

Find out more information

17 January – Gantry installation: Boondall

From late January until early March 2018, works will be undertaken to install the foundations and support pillar for a new gantry over the motorway at Boondall.

Find out more information

10 January – Gateway Motorway access track construction (Depot Road service lane)

Work will be undertaken to construct a permanent access track alongside the southbound Gateway Motorway lanes at Deagon. Work is scheduled to commence from mid-January and take approximately six weeks to complete.

Find out more information

5 January – Nundah Creek bridge piling works and Gateway Motorway works at Nudgee

From mid-January 2018 until late February 2018, piling works to construct the final bridge foundations for the new northbound bridge over Nundah Creek will be undertaken. Additionally, works to install permanent concrete barriers, guardrail and an overhead gantry sign will be undertaken  in Nudgee.

Find out more information

19 December – Extended changes to Nudgee Waterhole Reserve parking

Due to ongoing road construction in the area, the Nudgee Waterhole Reserve car park on Nudgee Road will remain temporarily closed until mid-2018. Alternate parking is available next to the Banyo Football Club on Childs Road.

Find out more information

15 December – Extended temporary shared pathway closure at Boondall

Due to ongoing bridge construction works on the Gateway Motorway over Sandgate Road/Braun Street and the Shorncliffe rail line, a section of the shared pathway between Boondall Train Station and the Cabbage Tree Creek pedestrian/cycle bridge will remain closed to all users until mid-2018.

View detour information


15 August – Sandgate Road-Holroyd Street intersection upgrade and signalisation

From late August, works will commence to upgrade the Sandgate Road-Holroyd Street intersection at Boondall to improve access to North Boondall train station and the new shared pathway alongside the Gateway Motorway.

Find out more information

Last updated
16 March 2018